MATRIX TEAM MEETING

Texas Die Casting – TOC Memo

Date: August 26, 2003

To: Bill Evans, Billy Diviney, Martha Baker and Mike Korsmo

Cc: John Howze, David Pack, Scott Daniel, John Oxton, Joe McKeown

RE: PART NUMBER MATRIX TEAM MEETING

1.Identify the Constraint (State the Problem):

Wrong part numbers are set-up in tools and ran in production


2.Exploit (Define causes and cures):

POSSIBLE CAUSES:

POSSIBLE CURES (ACTION ITEMS):

3.Subordinate (Involve\train others):

1. Matrix Team to design and implement matrices, picture books and work instructions required

   a. Team members include: Bill, Billy, Martha, David and Terry


b. MEETING ON AUGUST 25, 2003 at 2:00 pm


* Develop (3) Books – Mike

1. (1) Book for each QA, Tool Room, and Front Office (on Cabinet by Martha)

2. Sleeved page protectors, Customer dividers

3. Develop a standard page format for the book with Customer, P/N, Rev and Date

4. Books to be controlled as documents by Mike


* “Old” matrices from Tool Room – Bill and Billy

1. Bill to gather all old guides for customers - I, W, H, etc.

2. Billy to review, update and submit new guides using the standard form


* Customer W – Martha

1. Martha to get updated approval list and matrix from John Oxton

2. Mike and Bill are to ensure the part boards are up to date


* Customer I – Terry

1. Start with X Series Body Part numbers and tools

2. Make note of which tools are approved


* Customer H – Terry

1. Need guide for X, E and M

2. Pictures of new part numbers



* After these are completed the team will proceed with other customers



[back to 5 step examples]